Brickwork, interior painting, and new windows installed
At the Northeast façade, brick veneer is beginning to be installed. Interior painting has started on the ground floor as the interior takes shape.
Concrete continues with the pouring of the loading dock adjacent to the new kitchen.
Exterior sheathing completed within the courtyard.
Roofers have completed over half the roof, allowing for trades to work in a dry building underneath.
Windows are being set on the interior.
Ductwork within the gymnasium now spans across the ceiling.