The roofing is complete with the building interior protected from above.

  • With the building now dry, installation of the kitchen walk-in refrigerator is underway.

  • The plumber and electrician continue to push up through the building, as the mason and drywall contractor continue to wrap the building.

  • The final steel beams have been laid with the completion of the loading dock area.

  • The gymnasium is now enclosed as the exterior doors have been set.

  • Site work continues, with the retaining walls behind the building now permitted to begin.