The roofing is complete with the building interior protected from above.
With the building now dry, installation of the kitchen walk-in refrigerator is underway.
The plumber and electrician continue to push up through the building, as the mason and drywall contractor continue to wrap the building.
The final steel beams have been laid with the completion of the loading dock area.
The gymnasium is now enclosed as the exterior doors have been set.
Site work continues, with the retaining walls behind the building now permitted to begin.