Phase 1, Parking Desk & Phase 2-Aux Gym, Auditorium Updates

Phase 1 Building

  • Black Box completed.

  • Greenhouse Installed.

  • Old Georgetown Rd Thermal Striping completed this week. Traffic Lights to be turned on in the coming weeks with SHA permission.

 

Parking Deck

  • Underground Piping to be completed in next week.

  • Upper-level Garage Slabs/Wash Outs completed.

  • lower-level garage slab to be poured in next month.

  • Sprinkler System being installed.

  • Electrical Rough-in ongoing

 

Phase 2-Aux Gym, Auditorium, and Ball Fields

  • Perimeter surveying has been completed.

  • Plan to break ground in the next month pending weather.

  • Tree removal to begin in next few weeks.