Phase 1, Parking Desk & Phase 2-Aux Gym, Auditorium Updates
Phase 1 Building
Black Box completed.
Greenhouse Installed.
Old Georgetown Rd Thermal Striping completed this week. Traffic Lights to be turned on in the coming weeks with SHA permission.
Parking Deck
Underground Piping to be completed in next week.
Upper-level Garage Slabs/Wash Outs completed.
lower-level garage slab to be poured in next month.
Sprinkler System being installed.
Electrical Rough-in ongoing
Phase 2-Aux Gym, Auditorium, and Ball Fields
Perimeter surveying has been completed.
Plan to break ground in the next month pending weather.
Tree removal to begin in next few weeks.