Phase 1, Parking Desk & Phase 2-Aux Gym, Auditorium Updates
Phase 1 Building
- Black Box completed. 
- Greenhouse Installed. 
- Old Georgetown Rd Thermal Striping completed this week. Traffic Lights to be turned on in the coming weeks with SHA permission. 
Parking Deck
- Underground Piping to be completed in next week. 
- Upper-level Garage Slabs/Wash Outs completed. 
- lower-level garage slab to be poured in next month. 
- Sprinkler System being installed. 
- Electrical Rough-in ongoing 
Phase 2-Aux Gym, Auditorium, and Ball Fields
- Perimeter surveying has been completed. 
- Plan to break ground in the next month pending weather. 
- Tree removal to begin in next few weeks. 