Phase 1 Building
Old Georgetown Rd Traffic Signal is Complete.
Tennis Courts scheduled for Paving this Saturday.
Greenhouse Installed. Waiting on design details for Electrical and Mechanical.
Parking Deck
Underground electric duct bank and rough in is complete.
Underground storm Piping is completed.
lower-level garage slab to be poured soon once subgrade is addressed.
Sprinkler System mains and branch lines are installed at lower-level.
Glass/Windows installed at Stairwells.
Railings being installed, Light Poles to follow.
Phase 2-Aux Gym, Auditorium, and Ball Fields
Tree removal and clearing has begun a few weeks ago.
Aux Gym and Auditorium are being put on grade.