Phase 1 Building

  • Old Georgetown Rd Traffic Signal is Complete.

  • Tennis Courts scheduled for Paving this Saturday.

  • Greenhouse Installed. Waiting on design details for Electrical and Mechanical.

 

Parking Deck

  • Underground electric duct bank and rough in is complete.

  • Underground storm Piping is completed.

  • lower-level garage slab to be poured soon once subgrade is addressed.

  • Sprinkler System mains and branch lines are installed at lower-level.

  • Glass/Windows installed at Stairwells.

  • Railings being installed, Light Poles to follow.

 

Phase 2-Aux Gym, Auditorium, and Ball Fields

  • Tree removal and clearing has begun a few weeks ago.

  • Aux Gym and Auditorium are being put on grade.