• Parking Structure and Exterior of Building

    • Traffic Signalization plans are under construction with the medians being poured currently. Traffic poles will be installed prior to Christmas. Signalization programing will be complete by the middle of January.

    • Construction of the parking deck is under way. The precast concrete structures are now being set with electrical, mechanical, and elevator contractors to follow behind.

    • The canopies at the main entrance and gym lobby are nearing completion and should be done within the next three weeks.