Exterior Walls Complete for Parking Deck
Interior of Building
The building is complete and has been handed over to MCPS.
The black box theater is under construction.
Exterior of Building
Traffic Signalization plan is under construction.
Construction of the parking deck is under way. All concrete exterior walls are poured and braced, awaiting precast concrete pieces to be set. Backfilling of the structure is underway.
The canopies at the main entrance and gym lobby are framed and ready for roofing.