Phase 1, Parking Deck & Phase 2 Updates

Woodward HS Updates:

Phase 1 Building

  • Black Box completed.

  • Greenhouse Installed.

  • Old Georgetown Rd Thermal Striping completed this week. Traffic Lights to be turned on in the coming weeks with SHA permission.

Parking Deck:

  • Underground Piping to be completed in next week.

  • Upper-level Garage Slabs/Wash Outs completed.

  • lower-level garage slab to be poured in next month.

  • Sprinkler System being installed.

  • Electrical Rough-in ongoing

Phase 2-Aux Gym, Auditorium, and Ball Fields

  • Perimeter surveying has been completed.

  • Plan to break ground in the next month pending weather.

  • Tree removal to begin in next few weeks.

Previous
Previous

Phase 1 Building, Parking Deck & Phase 2- Aux Gym, Auditorium & Ball Field

Next
Next

Parking Deck / Updates