Phase 1, Parking Deck & Phase 2 Updates
Woodward HS Updates:
Phase 1 Building
Black Box completed.
Greenhouse Installed.
Old Georgetown Rd Thermal Striping completed this week. Traffic Lights to be turned on in the coming weeks with SHA permission.
Parking Deck:
Underground Piping to be completed in next week.
Upper-level Garage Slabs/Wash Outs completed.
lower-level garage slab to be poured in next month.
Sprinkler System being installed.
Electrical Rough-in ongoing
Phase 2-Aux Gym, Auditorium, and Ball Fields
Perimeter surveying has been completed.
Plan to break ground in the next month pending weather.
Tree removal to begin in next few weeks.