Phase 1 Building, Parking Deck & Phase 2- Aux Gym, Auditorium & Ball Field
Woodward HS Updates:
Phase 1 Building
Old Georgetown Rd Traffic Signal is Complete.
Tennis Courts scheduled for Paving this Saturday.
Greenhouse Installed. Waiting on design details for Electrical and Mechanical.
Parking Deck:
Underground electric duct bank and rough in is complete.
Underground storm Piping is completed.
Lower-level garage slab to be poured soon once subgrade is addressed.
Sprinkler System mains and branch lines are installed at lower-level.
Glass/Windows installed at Stairwells.
Railings being installed, Light Poles to follow.
Phase 2-Aux Gym, Auditorium, and Ball Fields
Tree removal and clearing has begun a few weeks ago.
Aux Gym and Auditorium are being put on grade.