Phase 1 Building, Parking Deck & Phase 2- Aux Gym, Auditorium & Ball Field

Woodward HS Updates:

Phase 1 Building

  • Tennis Courts – Paving Competed. Fencing to resume week of 4.21.2025

  • Greenhouse Installed. ASI  085 received for the Greenhouse revisions distributed to trades 4.14.25

Parking Deck:

  • Railings installation complete

  • Canopy main entrance bar completed

  • All light Poles installed

  • Concrete for slab on grade is in progress with pours week of 4.14.2025 and  4.21.2025

  • CMU walls set to commence within next few weeks once slab on grade is completed

Phase 2-Aux Gym, Auditorium, and Ball Fields

  • Tree removal and clearing complete

  • Aux Gym and Auditorium are on grade

  • Installation of HDPE Piping has begun