Superstructure Continues, Waterproofing Begins

Earthwork, concrete, masonry, underground utilities, steel, and site retaining walls are ongoing as the waterproofing begins.

  • Continuing concrete slab-on-grade at the lower end of the building along with pours at the lower-level concrete foundations and walls.

  • Moving along with steel erections at the north end of the building.

  • Site retaining walls at the south end of the property are ongoing.

  • Plumbing and electrical rough-ins are following our concrete foundations.

  • Currently building masonry walls within the interior of the building.

  • Waterproofing began below grade and around the building’s exterior.