Geopier Crews Return for Upper Level

Earthwork, concrete, masonry, underground utilities, steel, site retaining walls, and waterproofing are ongoing, as the cold-formed metal framing begins.

  • Currently prepping ground floor concrete slab on grade at the South end of the building. Preparing the North end of the 1st floor for concrete foundations.

  • Steel erections are moving along at the center of the building.

  • Site retaining walls at the south end of the property are ongoing.

  • Plumbing/ electrical rough-ins are following our concrete foundations and metal deck installations.

  • Waterproofing follows the ongoing installation of the masonry and concrete walls.

  • Cold-formed metal framing started working on the mockup sample. The interior building layout and wall construction will begin this month.