With Exterior Doors In Place, Heating Allows For More Interior Work

  • Exterior hollow metal doors are now hinged, allowing the building to be sealed off from the outside.

  • With the building closed, we have begun heating the building with temp heaters.

  • Rolling doors have been installed in the cafeteria area, and the Blackbox room.

  • Heating has allowed for flooring to commence on the upper floors, along with casework.

  • The electricians, HVAC, and plumbing contractors continue to work above the ceilings, going from third floor down while the ceiling contractor follows.

  • Interior finishes including painting and window installation continue to work their way down.

  • Metal panels continue to wrap the southern side of the building, moving in two directions now, west and north.

  • The green roof is complete, with the entirety of the roof covered.

  • Sidewalk installation is underway in the south parking lot, the asphalt paving shall commence in the parking area if weather permits.

  • Site landscaper continues to lay sod around the site where we have finished grade. This will continue along the south side of the property.