With Warm Weather on the Horizon, Finishes Heat Up!

  • Flooring continues, now finishing the corridors on the second and third floors.

  • The resinous flooring in stair 3 is finished, with the contractor now working on stair 4.

  • Casework and display cases continue to be assembled top floor down.

  • Metal lockers are following the casework from the top down.

  • Gym bleachers are fully assembled.

  • The plumber and electrician continue to work on the finished details for bathrooms and classrooms.

  • Metal panels continue to go up around the building, with the eastern side of the building nearing completion. The courtyard work is also 100% complete, allowing for more crews to work on the outside.

  • With the completion of the stormwater management systems in the eastern parking lot and good weather ahead, site pavement will begin in this next month.

Previous
Previous

Progress continues for both interior and exterior work.

Next
Next

Flooring continues, site work progresses, and metal panels are nearing completion!