Progress continues for both interior and exterior work.

  • Interior of Building

    • Final Paint on 2nd and 3rd Floors.

    • Flooring is currently being installed on the 2nd Floor, 1st floor and moving to the Ground Floor

    • Resinous Flooring has been completed in 2 of the 4 Main Stairways. Stair 1 is ongoing.

    • Casework and Metal Lockers are ongoing on the 1st and Ground Floors.

    • Acoustical Panels have been installed in the Gym, Wrestling Room, and Dance Room.

    • Window Treatments are being installed on the 3rd Floor.

    • Markerboards are being installed on 3rd and 2nd Floors.

  • Exterior of Building

    • Bus Parking Loop has been base paved.

    • Final Grading continues around the North and East of the site.

    • Site Concrete - Curbs and Sidewalks are being installed East of the building moving to the North of the building.

    • Storm Water Management and Water are ongoing.

    • Metal Panels are finishing up at the SW corner and the South Panels are to be completed in the next few weeks.