Progress Continues with Interior and Exterior Work!
Interior of Building
Ceiling tile being installed on the 3rd floor.
Flooring continues on 1st floor and ground floor.
Resinous flooring has been completed in all 4 main stair ways.
The gym floor has been lined and sealed.
Mirrors are being installed in the black box and dance rooms.
Elevator work has commenced.
Exterior of Building
Telecom communications duct bank complete running into the building.
Installation of the bio ponds at the front of the building has started.
Metal Panels are nearing completion with the south façade being the final area to finish.
Fencing along the block walls continues near the bus loop parking lot.
Site sidewalks around the exterior continue to be poured.