Progress Continues with Interior and Exterior Work!

  • Interior of Building

    • Third floor classrooms have been final cleaned and waxed. Work has started this week on the second floor classrooms.

    • Flooring continues on 1st floor and ground floor.

    • Casework continues throughout the second, first, and ground floors.

    • Elevator work nears completion.

    • Electrical and Plumbing contractor are prepared for unit commissioning and startup.

  • Exterior of Building

    • Curb and gutter work has started in the front of the building.

    • Metal Panels are nearing completion with the south façade being the final area to finish.

    • Fencing along the block walls has finished.

    • Site sidewalks around the exterior continue to be poured. 