Final Touches Underway as Building Nears Completion!

  • Interior of Building

    • Column Covers are placed and painted.

    • Windowsills are being placed in classrooms throughout the building.

    • The water is now turned on and running.

    • The painting contractor is working throughout the building making final touch ups.

    • Electrical contractor finishing programming on all lights.

    • MCPS has completed installation of all classroom furniture.

    • The Black box theater electrical work continues, with flooring soon to follow.

    • Decorative Rails are in place at Stairs A & B.

    • Gym equipment is being placed in the weight room.

    • The Northwood Logo has been placed in the center of the basketball court.

    • All corridors on floors 1-3 are waxed with MCPS staff beginning to do final waxing in classrooms.

  • Exterior of Building

    • Paving has been completed in the rear of the building.

    • High strength concrete will be finalized in rear of building by end of week.

    • State highway work at the entrances continues.

    • Placement of the asphalt for the tennis courts will begin this next week.

    • Footings and foundation walls are being poured for the parking structure.

    • The gas company has finalized connections.

    • The surplus of dirt in the rear of the building has been removed.

    • Excavation for the underground storm water management system at the rear of the property has commenced.