Site Work Ramps Up as Roofer Prepares to Place the Green Roof

  • Metal panel installation has started on the southeastern side of the building.

  • Wood doors are now onsite and are being stored in a climate-controlled room on the ground floor of the building.

  • The courtyard is backfilled, with topsoil and sod installation coming next.

  • Insulation and drywall work continues through the interior.

  • Kitchen equipment is now in the building.

  • Storm water management systems are being placed on the eastern side of the building, allowing the electrician to continue building out their duct bank for permanent power installation.

  • The green roof placement will start next week.