Site Work Ramps Up as Roofer Prepares to Place the Green Roof
Metal panel installation has started on the southeastern side of the building.
Wood doors are now onsite and are being stored in a climate-controlled room on the ground floor of the building.
The courtyard is backfilled, with topsoil and sod installation coming next.
Insulation and drywall work continues through the interior.
Kitchen equipment is now in the building.
Storm water management systems are being placed on the eastern side of the building, allowing the electrician to continue building out their duct bank for permanent power installation.
The green roof placement will start next week.